Default I need desperate help for homework with MRP planning Each unit of A is

composed 1 of unit of B, 2 units of C,? Each unit of A is composed 1 of unit of B, 2 units of C, and 1 unit of D.C is composed of 2 units of D and 3units of E.Items A,C,D and E have on-hand inventories of 20, 10, 20 and 10 units. Item B has scheduled receipt of 10 units in period 1 & C has 50. Lot-for-lot is used for items A & B C requires 50 units.D & E requires 100 & 50.Lead times 1 period for A B C, and 2 for D & E.Gross requirements for A are 30 in period 2, 30 in per.5 and 40 in per 8. Find planned order releases for all periods.

***I Did the bill of materials structure tree, but I am stuck at gross requirements for A. It says that A requires 30 in period 2, 30 in period 5 and 40 in period 8. From period 2 to 5, Do I add those two together to equal 60? or just push 30 from period 2 to cover the 30 for period 5, leaving it at 30????
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Reply


Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


All times are GMT. The time now is 04:48 PM.


Powered by vBulletin® Version 3.6.8
Copyright ©2000 - 2010, Jelsoft Enterprises Ltd.

Web Hosting by Chime Host